Executive Summary
Overview:
This week, we completed the Excavation of foundation trenches, fabrication of pad foundation and starter column reinforcements and placement of strip foundation concrete for the duplex project. We encountered issues site water supply, and we are on track for the next week.
ย Progress Overview
Milestones Achieved
- Setting out
Tasks Completed
- Excavation of Foundation Trenches
- Fabrication of Pad and Starter Column Reinforcements.
- Placement of Strip Foundation Concrete.
Current Status
Project Schedule:
Budget Status:
Project Pictures/Videos
Issues and Resolutions
Current Issues
Water availability is a challenge on site.
Resolution Actions
We propose that a generator should be permanently stationed on site for pumping of water as required.
Next Steps
- Continuation and Completion of Installation of Pad and Starter Column Reinforcement.
- Continuation and completion of placement of Pad Foundation concrete placement.
- Blockwork to DPC level.
- Carpentry on Starter Columns.