google.com, pub-8312298091109125, DIRECT, f08c47fec0942fa0

Week 2 (10/08/2024)

Executive Summary


Overview:

This week, we completed the placement of pad foundation concrete, Carpentry on Starter column formwork, Placement of starter column concrete, and fabrication and installation of tie beam reinforcementย  for the duplex project.

ย Progress Overview


Milestones Achieved

  • Setting out

Tasks Completed within Current Milestone Target

  • Excavation of Foundation Trenches
  • Fabrication of Pad and Starter Column Reinforcements.
  • Placement of Strip Foundation Concrete.
  • Placement of Pad Foundation Concrete.
  • Blockwork to DPC level.
  • Carpentry on Starter Column Formwork.
  • Placement of Starter Column Concrete.
  • Fabrication and Installation of Tie Beam Reinforcement

Current Status


Project Schedule:

% Tasks Completed: 100

Budget Status:

% Value Earned: 100

Project Pictures/Videos

 

 

Issues and Resolutions


Current Issues

  • Provision of sub standard Planks for formwork.
  • Planks provided got exhausted while the work was ongoing.

Resolution Actions

We propose that standard saw mill planks be procured going forward. This will ensure that all concrete works will be according to the desired specifications.

Next Steps


  • Continuation and Completion of Carpentry on Tie Beam Formwork.
  • Continuation and completion of placement of Tie Beam Concrete.
  • Continuation and completion of Filling of Foundation.
  • Compaction of Foundation Fill.
Open chat
Hello 👋
Can we help you?